FOUR OUT OF SIX: THE INSTALLATION OF MACHINES IN THE CMO CONTINUES

27.09.2024

Within the framework of the investment project "Organization of production of large-sized products for high-power gas turbine engines", the installation of turning and carousel machines with numerical control for machining large diameter rings continues on the production areas of the machining shop.

To date, four pieces of equipment have been installed out of the six planned ones. The assembly and installation of the equipment is carried out by specialists of the Chief Engineer service of Ruspolimet JSC and Start Plant LLC. According to the schedule, two more pieces of equipment are expected to be delivered before the end of this year. The foundations for them have already been prepared. 

The implementation of the above investment project allows the company to develop a new direction in the machining of rings – the production of large-sized products made of heat-resistant alloys, as well as expand the range and increase production volumes.